Published on 31st May 2014
Taunton's replacement for the former 40 Steps footbridge finally took a step closer to reality on Saturday 31st May 2014.
The first sections of the main bridge span arrived on site at Chip Lane during Saturday afternoon along with a multitude of lifting equipment from Ainscough Lifting. The bridge was transported to Taunton on three separate oversized loads, which were then held at Taunton Deane Services before picking up their allotted escort vehicles into Taunton via the A38. Nusteel (who have manufactured the bridge) have two overnight work windows in order to join the bridge sections together (this weekend) and then lift into position (next weekend). During each weekend Ainscough will be providing the lifting power via their 200 Tonne and 500 Tonne cranes, these will travel to Taunton each weekend for the required lifts.
Unfortunately we are able to confirm that the main span of the bridge is completely enclosed and meshed in, with no opportunity for a photographic viewpoint. This also raises questions about personal safety of persons using the bridge, as their is also no obvious way persons can be seen while walking through the bridge from the outside. The side panels also provide a perfect blank canvas for graffiti to be applied. We can only hope that some form of photographic vantage point will be possible from the ramped walkways of the bridge which will open at a later date.